Victoria Park's Construction Isn't One Project. It's Three.

September 17, 2026

"The neighborhood is split into 2 different basins," David Castro, the senior engineer overseeing Victoria Park's stormwater redesign, told the city's Infrastructure Task Force this fall. He was talking about drainage geometry, but the line works as a description of the whole neighborhood right now. Ask three different residents what's tearing up their street and you'll get three different answers, because they're all correct. There isn't one long construction project moving through Victoria Park. There are three, run by three different contractors, on three different clocks, and none of them will finish at the same time.

If you've watched a crew wrap up on your block and assumed the disruption was winding down, it's worth knowing which project you actually watched finish. The one that matters most for how this neighborhood handles the next big rain hasn't even reached its halfway point.

Three Projects, Three Timelines

Project Contractor What It Touches Where It Stands
Stormwater Improvements David Mancini & Sons, Inc. New pump station, roughly 43,000 feet of new pipe, a raised seawall near Gateway Terrace Broke ground February 2, 2026; budgeted at 18 to 24 months
Sewer Force Main Relining Lanzo Construction Co. Cured-in-place pipe lining, moving street by street Started November 2025; current segment runs August through October 2026
Watermain Replacement City of Fort Lauderdale Public Works About 60,000 feet of new 6-inch and 8-inch main replacing old 2-inch lines Ongoing, no published completion date

Three separate scopes of work, three separate budgets, three separate reasons your street might be closed on a given week. Here's what each one is actually doing.

The One That Fixes the Flooding

The stormwater project is the big one, both in dollars and in what it's meant to solve. The city's Infrastructure Task Force reviewed the final design in the fall of 2025: roughly 370 new drainage structures, about 12,000 linear feet of vegetated swales, exfiltration trenches on the higher ground, and a new pump station built into the neighborhood's east basin. David Mancini & Sons, Inc. was awarded the contract, and per the Victoria Park Civic Association, the total project cost lands around $33 million.

Part of the scope includes raising the seawall on the parcel just north of Gateway Terrace, which came up specifically at the task force meeting because that land sits next to the Gateway Terrace Apartments. Staff asked to bring the property owner into the planning conversation directly, since work on adjacent private seawalls affects how well the public side performs. City staffer Nancy Gassman was candid about the limits of what the public project alone can fix, noting the city still doesn't have a formal program to help private property owners raise their own seawalls, though it's part of what Fortify Lauderdale is exploring next.

Construction on this piece began February 2, 2026. At 18 to 24 months, that puts a realistic finish somewhere in the second half of 2027 to early 2028. This is the project residents should track if they care about how the neighborhood handles the next serious rain event, because it's the one actually adding pumping capacity and new pipe capacity, not just maintaining what's already there.

The One That Keeps Moving Down the Block

The sewer force main relining is a different animal entirely. This is Lanzo Construction Co. running cured-in-place pipe lining, a trenchless method that rehabs the inside of aging sewer pipes without digging up the whole street. It's one piece of a much larger citywide contract, roughly 23,370 feet of sewer pipeline running from Sunrise Boulevard to the George T. Lohmeyer Wastewater Treatment Plant, which is why the crews keep resurfacing on different Victoria Park blocks long after the first announcement. In November 2025, work opened on two fronts at once: NE 14th Avenue between NE 4th Street and NE 5th Court, NE 14th Avenue between NE 6th Street and NE 9th Street, and NE 9th Street between NE 14th and NE 15th Avenues, alongside a separate stretch covering NE 16th Avenue, NE 9th Street, and NE 18th Avenue.

The original estimate had the first of those segments wrapped by February 2026. It didn't happen on schedule. According to VPCA's own project updates, the completion slipped to August 2026 because of extended pressure testing on the newly lined pipe. By the time that segment closed out, a new one had already opened on another stretch of streets, beginning August 3, 2026 and expected to run through October 2026.

That six-month slip on a single, relatively short segment is worth sitting with. It's not a sign anything went wrong. Pressure testing on relined pipe takes as long as it takes, and rushing it defeats the purpose. But it does mean the honest answer to "when is this done" is "check which segment they're on now," not "read the original press release."

The One Nobody Notices Until Their Water Pressure Changes

The third project is the quietest because it doesn't generate the same visible disruption as a stormwater dig or a sewer relining crew. The city's watermain project is replacing roughly 60,000 feet of old 2-inch water main with new 6-inch and 8-inch pipe, plus new fire hydrants and individual service connections to each home. The stated benefits are better water flow, better fire protection, and higher system pressure, all of which matter more the older a neighborhood's original infrastructure gets. Victoria Park was platted in 1925 by developer Alfred G. Kuhn, and the water system running under its streets was laid out for that era's demands, not today's.

The city's FAQ on this project makes one thing explicit: residents won't lose water service during construction except in an emergency. The switch from old main to new happens only after the new line is tested and ready, and the changeover itself is quick. Roads affected by the work get repaved as part of the scope, which is the detail residents actually notice months later when a street that used to have visible patch lines suddenly doesn't.

What Already-Finished Neighborhoods Suggest About Timelines

Victoria Park isn't the first neighborhood to go through this. It's one of seven identified in the city's broader stormwater push, alongside Edgewood, River Oaks, Durrs, Dorsey Riverbend, Southeast Isles, and Progresso Village. Edgewood and River Oaks have already finished their projects. Durrs and Dorsey Riverbend got their new $67.8 million stormwater pump station this past spring, opened in April 2026, three years after a 2023 storm dumped more than 25 inches of rain on parts of the city and left those neighborhoods' streets and yards under water knee deep, by one resident's account.

Victoria Park is grouped with Progresso, Southeast Isles, and Melrose Manors as the next set of Phase 1 neighborhoods to complete, and city officials have said those projects should wrap within roughly three years of that April 2026 announcement. The broader Fortify Lauderdale initiative carries an estimated price tag near $1.6 billion citywide, funded through a mix of stormwater fees, grants, and bond financing.

None of this means Victoria Park's timeline will slip the way the sewer segment did. But the precedent is useful context: infrastructure projects of this scale rarely finish exactly on the first estimate, and the neighborhoods ahead of Victoria Park in the queue took real time to get from design to ribbon cutting.

Finding Out What's Happening On Your Block

Because these are three unrelated projects with three unrelated schedules, the fastest way to get a straight answer about your specific street is to go directly to the source rather than guess from what you see out your window.

  • For stormwater and drainage questions, Public Works contact Deborah Cueva takes street-specific inquiries at [email protected] or 954-828-5807.
  • For the sewer force main relining, there's a dedicated project hotline at 1-800-214-4095.
  • The Victoria Park Civic Association posts updates on all three projects as schedule changes come in from the city, and held its most recent monthly meeting on September 2, 2026 at St. Anthony's Cafeteria.

If you're weighing what any of this means for a Victoria Park property, whether you're staying put through the work or thinking about what comes after it wraps, our Victoria Park neighborhood guide is a good next stop, and Elite Florida Homes tracks these kinds of infrastructure updates as part of understanding what's actually happening in the neighborhoods we work in, not just what's listed for sale in them.

Three crews, three contracts, three end dates. Knowing which one is on your street this month is the difference between wondering when the construction ends and actually knowing.